PERMIT APPLICATION COMMON
Where on your property are you working?:
The entire site
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
0
PERMIT TRACKING COMMON
Permit Issued Date:
01/12/2021
Inspections Completed Date:
07/21/2021
DEMOLITION INFO
Type of Demolition:
Demolition
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
6
Fill Depth in Feet (maximum):
6
Foundation Type:
Basement
Does anyone live or work here?:
No
Is the disposal site inside the city?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes