PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
0
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
04/24/2019
Permit Issued Date:
08/22/2019
Permit Remarks:
Prior to final inspection, verify there is access to the required on-site parking location.
a. This will require installation of a gate and removal of the low concrete wall currently located behind the fence.
b. If the gate is not installed or the concrete wall is not removed, then an alternative on-site parking location will need to be approved by an SDCI zoning reviewer.
CONSTRUCTION VALUATION INFO
Intake Value: New:
440260
Intake Value: Alteration:
94426
Total Intake Value:
534686
Issue Value: New:
149894
Issue Value: Alteration:
164966
Total Issued Value:
314860
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
Yes
Action Type:
Add/Alt
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
1
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
No
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
750 square feet or less
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
N/A
PARKING
# of Existing Onsite Parking:
2
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Offsite Parking Location:
N/A
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Occupied by Property Owner
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Unknown