PERMIT APPLICATION COMMON
Where on your property are you working?:
in existing basement, 3rd floor and rebuilding existing garage roof
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
60000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
08/19/2020
Permit Issued Date:
07/29/2021
Inspections Completed Date:
10/26/2022
Certificate of Occupancy Issued Date:
10/27/2022
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
60000
Total Intake Value:
60000
Issue Value: New:
0
Issue Value: Alteration:
60000
Total Issued Value:
60000
BUILDING CODE INFO
What building code was used for your design?:
2015 SEBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
Add/Alt
Number of Existing Building Stories:
3
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Residential
Existing Occupancy:
R-2 Apartment/Condominium
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
9
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
9
# of Proposed Offsite Parking:
0
# of Proposed Accessible Parking:
0
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
2
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
Yes
Partial Fire Protection System:
No
Other Fire Protection System:
No
Other Type of Sprinkler System:
only 2 new unitd
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
electric wall heaters and exhaust fans
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Natural Gas
Data Center Building?:
No
Power is Sub-Metered?:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee