PERMIT APPLICATION COMMON
Where on your property are you working?:
back yard
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
150000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
01/14/2019
Permit Issued Date:
04/02/2019
Inspections Completed Date:
01/17/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
111088
Intake Value: Alteration:
0
Total Intake Value:
111088
Issue Value: New:
111088
Issue Value: Alteration:
0
Total Issued Value:
111088
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
750 square feet or less
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
5
Fill Depth in Feet (maximum):
5
Foundation Type:
Spread Footing
Does anyone live or work here?:
Yes
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4960
New Impervious Surface:
1268
New Plus Replaced Impervious Surface:
1268
Total Volume Managed by On-Site Stormwater Management (gallons):
0
Total Area Requiring Soil Amendment:
875
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
Yes