PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
0
PERMIT TRACKING COMMON
Review Level:
Dependent Building
Application Completed Date:
02/02/2018
Permit Issued Date:
06/12/2018
Inspections Completed Date:
02/28/2019
Permit Remarks:
Please issue when 6632195-CN-002 has been completed
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
DEMOLITION INFO
Type of Demolition:
Demolition