PERMIT APPLICATION COMMON
Where on your property are you working?:
2nd floor roof deck and various areas.
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
20000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
12/12/2018
Permit Issued Date:
11/19/2019
Inspections Completed Date:
08/16/2021
Certificate of Occupancy Issued Date:
08/16/2021
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
11122256
Intake Value: Alteration:
0
Total Intake Value:
11122256
Issue Value: New:
11122256
Issue Value: Alteration:
0
Total Issued Value:
11122256
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
5
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Main Existing Use of Building:
Residential
Existing Occupancy:
R-3 Single Family Dwelling
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
13
Fill Depth in Feet (maximum):
0
Foundation Type:
Spread Footing
Does anyone live or work here?:
No
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
3
# of Existing Offsite Parking:
0
# of Existing Accessible Parking:
0
# of Proposed Onsite Parking:
22
# of Proposed Offsite Parking:
0
Offsite Parking Location:
none
# of Proposed Accessible Parking:
2
# of Existing Bicycle Parking Spots:
0
# of Proposed Bicycle Parking Spots:
16
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
Yes
Partial Fire Protection System:
No
Fire Alarm:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Residential
Compliance Path:
Total UA Alternative
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
5.4 KW of PV solar on roof
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Resistance
Cooling Fuel Type Proposed: Residential:
Unknown
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
27879
New Impervious Surface:
15000
New Plus Replaced Impervious Surface:
24786
Total Volume Managed by On-Site Stormwater Management (gallons):
173496
Total Area Requiring Soil Amendment:
3093
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
3
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
3
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
95
Reuse Existing Side Sewer System:
No