PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
01/01/2019
Permit Issued Date:
07/11/2020
Inspections Completed Date:
06/07/2024
CONSTRUCTION VALUATION INFO
Intake Value: New:
912491
Intake Value: Alteration:
0
Total Intake Value:
912491
Issue Value: New:
955185
Issue Value: Alteration:
0
Total Issued Value:
955185
PERMIT APPLICATION COMMON
Where on your property are you working?:
THE ENTIRE SITE WILL BE AFFECTED BY THE SCOPE OF WORK
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
900000
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
3
Fill Depth in Feet (maximum):
2
Foundation Type:
Spread Footing
Does anyone live or work here?:
No
Is the disposal site inside the city?:
No
PARKING
# of Proposed Onsite Parking:
6
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will your application include a new standard plan?:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Pipe
Flow Control Standard:
Pasture
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
4800
New Impervious Surface:
1841
New Plus Replaced Impervious Surface:
3945
Total Volume Managed by On-Site Stormwater Management (gallons):
38266
Total Area Requiring Soil Amendment:
855
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
6
Reuse Existing Side Sewer System:
Yes