PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/04/2018
Permit Issued Date:
02/14/2019
Inspections Completed Date:
08/12/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
750000
Intake Value: Alteration:
0
Total Intake Value:
750000
Issue Value: New:
750000
Issue Value: Alteration:
0
Total Issued Value:
750000
Total Revision Value:
0
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
750000
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
TRAO License Issued
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
5
Fill Depth in Feet (maximum):
5
Foundation Type:
Spread Footing
Does anyone live or work here?:
Yes
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
New
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
No
Exit and Pathway Lighting:
No
Stairway Pressurization:
No
Smoke Removal System:
No
Emergency Generator:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4504
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
2716
Total Volume Managed by On-Site Stormwater Management (gallons):
38340
Total Area Requiring Soil Amendment:
1788
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
3
Reuse Existing Side Sewer System:
Yes