PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
12/05/2018
Permit Issued Date:
12/24/2019
Permit Remarks:
3/11/19 - SAC
Address changed from 4103 Fremont Ave N to 612 N 41st ST.
CONSTRUCTION VALUATION INFO
Intake Value: New:
652871
Intake Value: Alteration:
0
Total Intake Value:
652871
Issue Value: New:
722095
Issue Value: Alteration:
0
Total Issued Value:
722095
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
652871
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Occupied by Property Owner
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
2
Fill Depth in Feet (maximum):
6
Foundation Type:
Spread Footing
Does anyone live or work here?:
Yes
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Are you changing the envelope?:
Yes
Action Type:
New
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
6682519
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
3998
New Impervious Surface:
1387
New Plus Replaced Impervious Surface:
1830
Total Volume Managed by On-Site Stormwater Management (gallons):
46792
Total Area Requiring Soil Amendment:
781
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
5
Reuse Existing Side Sewer System:
Yes