PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
103505347
CONSTRUCTION VALUATION INFO
Intake Value: New:
132792149
Intake Value: Alteration:
0
Total Intake Value:
132792149
Issue Value: New:
135688765
Issue Value: Alteration:
0
Total Issued Value:
135688765
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
15
Number of Proposed Below-Grade Building Stories:
3
Number of Mezzanines:
0
Is this a high-rise?:
Yes
Is a certificate of occupancy required?:
Yes
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT Permit Accepted:
Yes
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
More than 1 cubic yard
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/06/2018
Permit Issued Date:
11/04/2019
Start of MUP Life:
01/12/2022
Inspections Completed Date:
06/13/2024
Certificate of Occupancy Issued Date:
06/13/2024
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
One Curb Cut, 30' wide located along valley Street about 37 west of the north east property corner. Separate Street Use permit required.
PARKING
Number of Existing Onsite Parking Spaces:
0
Number of Existing Offsite Parking Spaces:
0
Number of Existing Accessible Parking Spaces:
0
Number of Proposed Onsite Parking Spaces:
0
Number of Proposed Offsite Parking Spaces:
0
Offsite Parking Location:
0
Number of Proposed Accessible Parking Spaces:
0
Number of Existing Bicycle Parking Spots:
0
Number of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Exit and Pathway Lighting:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
No
Emergency Generator:
Yes
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Compliance Path:
Total Building Performance (TBP)
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Other
Cooling Fuel Type Proposed: Non-Residential:
Other
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
1
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
59818
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
59818
Total Volume Managed by On-Site Stormwater Management (gallons):
93359
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
4
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
2
Number of New Connections to the Side Sewer:
1
Reuse Existing Side Sewer System:
Yes