PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/10/2018
Permit Issued Date:
07/18/2019
Inspections Completed Date:
11/20/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
442577
Intake Value: Alteration:
0
Total Intake Value:
442577
Issue Value: New:
442577
Issue Value: Alteration:
0
Total Issued Value:
442577
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
442577
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
To permit a 10' curb cut approx. 5' east of west property line
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Action Type:
New
Is a certificate of occupancy required?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Unknown
SIDE SEWER INFORMATION
Related New Construction Project:
6675499
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
Formwer Combined
Total Disturbed Area:
5000
New Impervious Surface:
1642
New Plus Replaced Impervious Surface:
4009
Total Volume Managed by On-Site Stormwater Management (gallons):
57022
Total Area Requiring Soil Amendment:
991
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
6
Reuse Existing Side Sewer System:
Yes