PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
06/27/2018
Permit Issued Date:
09/03/2018
Inspections Completed Date:
12/14/2020
Certificate of Occupancy Issued Date:
12/14/2020
PERMIT APPLICATION COMMON
Where on your property are you working?:
Building A/B/C/D of Amgen Seattle HQ
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
20000000
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
20000000
Total Intake Value:
20000000
Issue Value: New:
0
Issue Value: Alteration:
20000000
Total Issued Value:
20000000
BUILDING CODE INFO
What building code was used for your design?:
2015 SEBC
Specific Building Code:
SEBC Prescriptive
Is this a substantial alteration?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
4
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
4
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Elevator Pressurization:
No
Stairway Pressurization:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Annual Energy Analysis
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Non-Residential:
Other
Cooling Fuel Type Proposed: Non-Residential:
Other
Special Requirements:
on site renewable C411,C406 included in C407 modeling. C412 solar readiness on A0.012. Phase ia( blgd ABCD + CUP) & ib (blgd. J+ common).
SIDE SEWER INFORMATION
Related New Construction Project:
6529069
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
Basic
Discharge Point:
Storm System
Total Disturbed Area:
576948
New Impervious Surface:
200000
New Plus Replaced Impervious Surface:
284301
Total Volume Managed by On-Site Stormwater Management (gallons):
2655418
Total Area Requiring Soil Amendment:
292646
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
Yes