PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
1048657
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/27/2018
Permit Issued Date:
04/15/2019
Inspections Completed Date:
11/25/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
1048657
Intake Value: Alteration:
0
Total Intake Value:
1048657
Issue Value: New:
1048657
Issue Value: Alteration:
0
Total Issued Value:
1048657
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
No
Action Type:
New
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
One curb cut 10' wide to be located along 11th AVE NE approximately 4.5 ft. north of the south property line.
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
6672144
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Infiltration
Flow Control Standard:
Pasture and Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
6192
New Impervious Surface:
3118
New Plus Replaced Impervious Surface:
5818
Total Volume Managed by On-Site Stormwater Management (gallons):
116211
Total Area Requiring Soil Amendment:
374
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
8
Reuse Existing Side Sewer System:
Yes