PERMIT APPLICATION COMMON
Where on your property are you working?:
New foundation under existing structure and changing the existing duplex into a 4 unit building.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
250000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
12/10/2018
Permit Issued Date:
12/13/2019
Inspections Completed Date:
07/29/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
250000
Total Intake Value:
250000
Issue Value: New:
0
Issue Value: Alteration:
250000
Total Issued Value:
250000
BUILDING CODE INFO
What building code was used for your design?:
2015 SEBC
Specific Building Code:
SEBC Prescriptive
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
2
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Main Existing Use of Building:
Residential
Existing Occupancy:
R-2 Apartment/Condominium
Will your application include a new standard plan?:
No
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
750 square feet or less
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
One curb cut, 10' wide located along W Fulton St about 19'-6" from the east proposer line.
PARKING
# of Existing Onsite Parking:
1
# of Proposed Onsite Parking:
1
# of Proposed Accessible Parking:
0
# of Proposed Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
No
Sprinklers Meet NFPA 13R:
Yes
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Residential
Compliance Path:
Total UA Alternative
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
4 Mini split heat pumps
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Cooling Fuel Type Proposed: Residential:
Electric Heat Pump
Special Requirements:
Green building checklist complies with DR 20-2017 for Green building certification