PERMIT APPLICATION COMMON
Where on your property are you working?:
MHS 11/27/18 changed address for WEST SFR from 4732 to 4730 7TH AVE NE
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
241053
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/20/2018
Permit Issued Date:
09/19/2018
Inspections Completed Date:
09/03/2019
Permit Remarks:
MHS 11/27/18 changed address for WEST SFR from 4732 to 4730 7TH AVE NE
CONSTRUCTION VALUATION INFO
Intake Value: New:
241053
Intake Value: Alteration:
0
Total Intake Value:
241053
Issue Value: New:
241053
Issue Value: Alteration:
0
Total Issued Value:
241053
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
New
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
3
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
1
Fill Depth in Feet (maximum):
1
Foundation Type:
Spread Footing
Does anyone live or work here?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
3208
New Impervious Surface:
1239
New Plus Replaced Impervious Surface:
1796
Total Volume Managed by On-Site Stormwater Management (gallons):
25363
Total Area Requiring Soil Amendment:
1412
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes