PERMIT APPLICATION COMMON
Where on your property are you working?:
Townhouse Units A-H
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
822542
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/27/2018
Permit Issued Date:
10/23/2019
Inspections Completed Date:
02/23/2022
Permit Remarks:
1. Priority green expedited. 2. To establish and maintain one (1) 10' curb cut on Linden Ave N, commencing 5' south of the northern property line.
CONSTRUCTION VALUATION INFO
Intake Value: New:
1319601
Intake Value: Alteration:
0
Total Intake Value:
1319601
Issue Value: New:
1319601
Issue Value: Alteration:
0
Total Issued Value:
1319601
BUILDING CODE INFO
What building code was used for your design?:
2012 SBC (Struct) and SRC (Arch)
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
1
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
To establish and maintain one (1) 10' curb cut on Linden Ave N, commencing 5' south of the northern property line.
PARKING
# of Existing Offsite Parking:
0
# of Proposed Onsite Parking:
2
# of Proposed Offsite Parking:
2
# of Existing Bicycle Parking Spots:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
TRAO License Issued
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Related New Construction Project:
6649960
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
6819
New Impervious Surface:
3639
New Plus Replaced Impervious Surface:
6257
Total Volume Managed by On-Site Stormwater Management (gallons):
52231
Total Area Requiring Soil Amendment:
562
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
8
Reuse Existing Side Sewer System:
No