PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
423886
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
05/31/2018
Permit Issued Date:
01/16/2020
Inspections Completed Date:
12/08/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
423886
Intake Value: Alteration:
0
Total Intake Value:
423886
Issue Value: New:
444018
Issue Value: Alteration:
0
Total Issued Value:
444018
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
Are you doing more than 2,000 square feet of earth disturbance?:
More than 750 square feet
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
PARKING
# of Existing Onsite Parking:
0
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
2
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
Bio-Engineer
Flow Control Standard:
Pasture and Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
2320
New Impervious Surface:
563
New Plus Replaced Impervious Surface:
1947
Total Volume Managed by On-Site Stormwater Management (gallons):
20010
Total Area Requiring Soil Amendment:
373
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
Yes