PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
30000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
06/13/2018
Permit Issued Date:
07/09/2018
Inspections Completed Date:
10/21/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
30000
Intake Value: Alteration:
0
Total Intake Value:
30000
Issue Value: New:
30000
Issue Value: Alteration:
0
Total Issued Value:
30000
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
none
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
558155
New Impervious Surface:
2688
New Plus Replaced Impervious Surface:
2688
Total Volume Managed by On-Site Stormwater Management (gallons):
19425
Total Area Requiring Soil Amendment:
150
SANITARY INFORMATION
Sanitary Type of Work:
None
Reuse Existing Side Sewer System:
No