PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
360000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
01/04/2018
Permit Issued Date:
08/07/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
360000
Intake Value: Alteration:
0
Total Intake Value:
360000
Issue Value: New:
0
Issue Value: Alteration:
0
Total Issued Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Units on Property
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
Addition/Alteration
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
None
Reuse Existing Side Sewer System:
No