PERMIT APPLICATION COMMON
Where on your property are you working?:
MHS 3/13/18 CHANGED ADDRESS FROM 2813 TO 2815 4TH AVE W FOR PARCEL B, LBA 3029682
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
574924
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/15/2018
Permit Issued Date:
12/06/2019
Inspections Completed Date:
06/04/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
574924
Intake Value: Alteration:
0
Total Intake Value:
574924
Issue Value: New:
491970
Issue Value: Alteration:
0
Total Issued Value:
491970
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
PARKING
# of Proposed Onsite Parking:
0
# of Proposed Offsite Parking:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
Yes
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
6503
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
5173
Total Volume Managed by On-Site Stormwater Management (gallons):
35568
Total Area Requiring Soil Amendment:
1330
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
5
Reuse Existing Side Sewer System:
No