PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
853608
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
02/21/2018
Permit Issued Date:
01/07/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
853608
Intake Value: Alteration:
0
Total Intake Value:
853608
Issue Value: New:
0
Issue Value: Alteration:
0
Total Issued Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
New
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
Yes
Pipe Lining in the Right-of-Way:
Yes
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
Yes
Excavation:
Yes
Roadway Restoration:
Yes
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Weep Hole
Total Disturbed Area:
5261
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
2838
Total Volume Managed by On-Site Stormwater Management (gallons):
44022
Total Area Requiring Soil Amendment:
2838
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
5
Reuse Existing Side Sewer System:
Yes