PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Institutional
Project Value:
1800000
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
01/04/2018
Permit Issued Date:
07/20/2018
CONSTRUCTION VALUATION INFO
Intake Value: New:
1800000
Intake Value: Alteration:
0
Total Intake Value:
1800000
Issue Value: New:
1800000
Issue Value: Alteration:
0
Total Issued Value:
1800000
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
0
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
Yes
Excavation:
Yes
Roadway Restoration:
Yes
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
1
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
10516
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
10516
Total Volume Managed by On-Site Stormwater Management (gallons):
54498
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Dwelling Units:
0
Reuse Existing Side Sewer System:
No