PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
11250380
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
04/11/2018
Permit Issued Date:
12/05/2019
Inspections Completed Date:
09/23/2021
Certificate of Occupancy Issued Date:
09/28/2021
CONSTRUCTION VALUATION INFO
Intake Value: New:
11250380
Intake Value: Alteration:
0
Total Intake Value:
11250380
Issue Value: New:
11250380
Issue Value: Alteration:
0
Total Issued Value:
11250380
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Existing Building Stories:
0
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
6
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
PARKING
# of Proposed Onsite Parking:
28
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Fire Alarm:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
Yes
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
Yes
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Commercial
Compliance Path:
Component Performance
Is there a fume hood?:
No
Is there a spray paint booth?:
No
Describe any other mechanical systems to be installed as part of this project.:
4.4 KW PV system on roof
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Resistance
Cooling Fuel Type Proposed: Residential:
Unknown
Special Requirements:
Applicant changed from prescriptive compliance to UA Component Performance compliance.
SIDE SEWER INFORMATION
Related New Construction Project:
6615994
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
14415
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
1294
Total Volume Managed by On-Site Stormwater Management (gallons):
83342
Total Area Requiring Soil Amendment:
1509
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
2
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Reuse Existing Side Sewer System:
No