PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
268459
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
10/26/2017
Permit Issued Date:
08/10/2018
Inspections Completed Date:
12/26/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
268459
Intake Value: Alteration:
0
Total Intake Value:
268459
Issue Value: New:
268459
Issue Value: Alteration:
0
Total Issued Value:
268459
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
New
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
0
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Special Requirements:
SEC 2015 EC - 1A, 3D, 5A, 5C
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
2500
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
2000
Total Volume Managed by On-Site Stormwater Management (gallons):
0
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Connections to the Side Sewer:
1
Number of New Dwelling Units:
1
Reuse Existing Side Sewer System:
No