HISTORICAL
Hansen APNO:
6610963
Hansen APKEY:
739251
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
15454258
CONSTRUCTION VALUATION INFO
Intake Value: New:
18395667
Intake Value: Alteration:
0
Total Intake Value:
18395667
Issue Value: New:
18395667
Issue Value: Alteration:
0
Total Issued Value:
18395667
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
Yes
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/20/2017
Permit Issued Date:
04/18/2018
Inspections Completed Date:
03/25/2020
Certificate of Occupancy Issued Date:
03/25/2020
Permit Remarks:
Alley dedication recording # 2018020500744
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Total UA Alternative
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Unknown
Cooling Fuel Type Proposed: Residential:
Unknown
Special Requirements:
PV on roof
Power is Sub-Metered?:
Yes
SIDE SEWER INFORMATION
Pipe Lining in the Right-of-Way:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
28577
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
28577
Total Volume Managed by On-Site Stormwater Management (gallons):
162461
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
3
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
No