PERMIT APPLICATION COMMON
Where on your property are you working?:
SOUTH SFR - 5513 4TH AVE NW
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
254195
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
01/26/2018
Permit Issued Date:
10/02/2018
Inspections Completed Date:
02/10/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
254195
Intake Value: Alteration:
0
Total Intake Value:
254195
Issue Value: New:
263828
Issue Value: Alteration:
0
Total Issued Value:
263828
BUILDING CODE INFO
What building code was used for your design?:
2015 SRC
Is this a substantial alteration?:
No
Action Type:
New
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Natural Gas
Special Requirements:
SEC 2015 EC - 1D, 3A, 5A, 5C
SIDE SEWER INFORMATION
Related New Construction Project:
6587920
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
3203
New Impervious Surface:
1824
New Plus Replaced Impervious Surface:
2316
Total Volume Managed by On-Site Stormwater Management (gallons):
23429
Total Area Requiring Soil Amendment:
887
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
2
Reuse Existing Side Sewer System:
No
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No