PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
4574933
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/13/2017
Permit Issued Date:
07/03/2018
Inspections Completed Date:
02/13/2020
Certificate of Occupancy Issued Date:
02/13/2020
CONSTRUCTION VALUATION INFO
Intake Value: New:
4574933
Intake Value: Alteration:
0
Total Intake Value:
4574933
Issue Value: New:
4574933
Issue Value: Alteration:
0
Total Issued Value:
4574933
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Exit and Pathway Lighting:
Yes
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Component Performance
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Unknown
Special Requirements:
C406.9/G2.05 and C406.6 DOAS/M0.01 Reference Drawing (pg. 116 in Plan SetV3). Plus, C411 is met via Exception #1 (see M0.01).
SIDE SEWER INFORMATION
Related New Construction Project:
6581551
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
11064
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
10950
Total Volume Managed by On-Site Stormwater Management (gallons):
63696
Total Area Requiring Soil Amendment:
114
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
2
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
Yes
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Unknown