HISTORICAL
Hansen APNO:
6612797
Hansen APKEY:
741227
PERMIT APPLICATION COMMON
Where on your property are you working?:
CHANGED ADDRESS FROM 2101 22ND AVE S TO 2100 S WALKER ST 11/14/17 JH
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Institutional
Project Value:
7923505
CONSTRUCTION VALUATION INFO
Intake Value: New:
7923505
Intake Value: Alteration:
0
Total Intake Value:
7923505
Issue Value: New:
7923505
Issue Value: Alteration:
0
Total Issued Value:
7923505
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
Yes
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
11/01/2017
Permit Issued Date:
09/18/2018
Inspections Completed Date:
12/16/2019
Certificate of Occupancy Issued Date:
12/16/2019
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Non-Residential:
Unknown
Special Requirements:
SEC C406: C406.2 & C406.6, SEC C411: PV
SIDE SEWER INFORMATION
Related New Construction Project:
6573122
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
Yes
Excavation:
Yes
Roadway Restoration:
Yes
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
1
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
2
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
Basic
Discharge Point:
Storm System
Total Disturbed Area:
46119
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
41945
Total Volume Managed by On-Site Stormwater Management (gallons):
225965
Total Area Requiring Soil Amendment:
4174
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
No