PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
1800000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
11/30/2016
Permit Issued Date:
03/29/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
1800000
Intake Value: Alteration:
0
Total Intake Value:
1800000
Issue Value: New:
1800000
Issue Value: Alteration:
0
Total Issued Value:
1800000
BUILDING CODE INFO
What building code was used for your design?:
2012 SBC
Specific Building Code:
2012 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
0
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Curb Cut Size and Location:
na
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
Addition/Alteration
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
19465
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
0
Total Volume Managed by On-Site Stormwater Management (gallons):
0
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
Addition/Alteration
Reuse Existing Side Sewer System:
Yes
PARKING
Number of Proposed Onsite Parking Spaces:
0
Number of Existing Bicycle Parking Spots:
0
Number of Proposed Bicycle Parking Spots:
0