PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
197433
PERMIT TRACKING COMMON
Review Level:
Full +
Application Completed Date:
11/03/2021
Permit Issued Date:
02/17/2022
Inspections Completed Date:
05/08/2026
Permit Remarks:
11/10/2021 RC - ADDRESS CHANGED FROM 1225 TO 1227 NE 96TH ST
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
77378
Intake Value: Alteration:
0
Total Intake Value:
77378
Issue Value: New:
81786
Issue Value: Alteration:
0
Total Issued Value:
81786
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC (Struct) and SRC (Arch)
Is this a substantial alteration?:
Yes
Are you changing the envelope?:
Yes
Action Type:
Add/Alt
Number of Existing Building Stories:
1
Number of Existing Below-Grade Building Stories:
0
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
PARKING
# of Existing Onsite Parking:
1
# of Proposed Offsite Parking:
1
Tenant Relocation Assistance
Residential Unit Occupancy:
All Residential Units Occupied by Property Owner
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Compliance Category:
Residential
Compliance Path:
Prescriptive
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Electric Heat Pump
Data Center Building?:
No
Power is Sub-Metered?:
No
SANITARY INFORMATION
Reuse Existing Side Sewer System:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Owner/Lessee
CONTRACTOR DISCLOSURE
I have submitted an application for a building permit from the City of Seattle. I believe the work authorized by this permit is exempt from having a registered contractor. I understand that I may be waiving certain rights that I might otherwise have under state law in any decision to engage an unregistered contractor to perform construction work.:
Yes