PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
7236697
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/18/2017
Permit Issued Date:
09/06/2019
CONSTRUCTION VALUATION INFO
Intake Value: New:
7236697
Intake Value: Alteration:
0
Total Intake Value:
7236697
Issue Value: New:
7236697
Issue Value: Alteration:
0
Total Issued Value:
7236697
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Is this a substantial alteration?:
No
Action Type:
New
Will you change the building use or occupancy?:
Yes
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
construct and maintain one residential curb cut 32 feet 7 inches wide along Highline Drive approximately 77 feet from the east property line.
PARKING
# of Proposed Onsite Parking:
21
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Component Performance
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Non-Residential:
Unknown
Special Requirements:
C411 + C406.5/G2.00 & A2.08
SIDE SEWER INFORMATION
Related New Construction Project:
6522966
Temporary Dewatering for Construction:
Yes
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
Pipe
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
7581
New Impervious Surface:
2100
New Plus Replaced Impervious Surface:
6657
Total Volume Managed by On-Site Stormwater Management (gallons):
0
Total Area Requiring Soil Amendment:
924
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Reuse Existing Side Sewer System:
No