PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
0
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
08/31/2018
Permit Issued Date:
02/29/2020
Inspections Completed Date:
04/23/2025
Certificate of Occupancy Issued Date:
04/23/2025
Permit Remarks:
10-foot curbcut located in the middle of the parcel.
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
6229191
Intake Value: Alteration:
0
Total Intake Value:
6229191
Issue Value: New:
6729998
Issue Value: Alteration:
0
Total Issued Value:
6729998
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
New
Number of Proposed Building Stories:
6
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Curb Cut Size and Location:
10-foot curbcut located in the middle of the parcel.
PARKING
# of Proposed Onsite Parking:
24
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) Unoccupied
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
Yes
Exit and Pathway Lighting:
Yes
Stairway Pressurization:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
Yes
Compliance Category:
Commercial
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
Heating Fuel Type Proposed: Residential:
Unknown
Special Requirements:
C411
Power is Sub-Metered?:
Yes
SIDE SEWER INFORMATION
Related New Construction Project:
6519858
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
Pipe
Flow Control Standard:
Pasture and Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Other
Discharge Point Other Type:
CULVERT
Total Disturbed Area:
12660
New Impervious Surface:
224
New Plus Replaced Impervious Surface:
10982
Total Volume Managed by On-Site Stormwater Management (gallons):
87269
Total Area Requiring Soil Amendment:
1678
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
71
Reuse Existing Side Sewer System:
No