HISTORICAL
Hansen APNO:
6516739
Hansen APKEY:
635531
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
94127654
CONSTRUCTION VALUATION INFO
Intake Value: New:
94127654
Intake Value: Alteration:
0
Total Intake Value:
94127654
Issue Value: New:
94127654
Issue Value: Alteration:
0
Total Issued Value:
94127654
BUILDING CODE INFO
What building code was used for your design?:
2012 SBC
Specific Building Code:
2012 SBC
Action Type:
New
Number of Proposed Building Stories:
35
Number of Proposed Below-Grade Building Stories:
5
Number of Mezzanines:
1
Is this a high-rise?:
Yes
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is the ground disturbance in an environmentally critical area?:
No
What is the amount of ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
12/21/2016
Permit Issued Date:
11/01/2017
Certificate of Occupancy Issued Date:
03/21/2024
Permit Remarks:
L16 mezzanine west edge move east to grid C in phase 3.
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
Yes
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Annual Energy Analysis
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Non-Residential:
Unknown
Special Requirements:
SEC C410: PV
SIDE SEWER INFORMATION
Pipe Lining in the Right-of-Way:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
19333
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
19333
Total Volume Managed by On-Site Stormwater Management (gallons):
52431
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
No