PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Institutional
Project Value:
17700000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
09/10/2014
Permit Issued Date:
03/12/2015
Inspections Completed Date:
05/18/2018
CONSTRUCTION VALUATION INFO
Intake Value: New:
0
Intake Value: Alteration:
17700000
Total Intake Value:
17700000
Issue Value: New:
0
Issue Value: Alteration:
17700000
Total Issued Value:
17700000
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
No
SDOT Permit Accepted:
No
BUILDING CODE INFO
What building code was used for your design?:
2012 SEBC Prescriptive
Specific Building Code:
2012 SEBC Prescriptive
Is this a substantial alteration?:
No
Are you changing the envelope?:
No
Action Type:
Add/Alt
Number of Existing Building Stories:
8
Number of Existing Below-Grade Building Stories:
1
Number of Proposed Building Stories:
8
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
No
Does anyone live or work here?:
No
Is the disposal site inside the city?:
No
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
No
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
No
Exit and Pathway Lighting:
No
Stairway Pressurization:
No
Smoke Removal System:
No
Emergency Generator:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
MECHANICAL DUCTWORK LOCATION
Is there any equipment inside?:
No
Is there any ground-mounted exterior equipment?:
No
Is there any wall-mounted exterior equipment?:
No
Is there any rooftop equipment? :
No
ENERGY CODE
Is any portion of the building semi-heated or unheated?:
No
Is there a commercial kitchen hood exhaust system?:
No
Is there a fume hood?:
No
Is there a spray paint booth?:
No
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Special Requirements:
Existing fuel sources. TI only. RJ 10/20/14.
Data Center Building?:
No
Power is Sub-Metered?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Side Sewer Conflict Description:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
SANITARY INFORMATION
Reuse Existing Side Sewer System:
No
SHORELINE MITIGATION SEQUENCE
Sequencing Required:
No