PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
1311856
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/07/2015
Permit Issued Date:
07/18/2019
Inspections Completed Date:
01/20/2023
Certificate of Occupancy Issued Date:
01/24/2023
Permit Remarks:
Priority Green Expedited Existing curb cut to be replaced with curb and sidewalk per SDOT standards.
CONSTRUCTION VALUATION INFO
Intake Value: New:
1311856
Intake Value: Alteration:
0
Total Intake Value:
1311856
Issue Value: New:
1311856
Issue Value: Alteration:
0
Total Issued Value:
1311856
Total Revision Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2012 SBC
Specific Building Code:
2012 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
4
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
Yes
Does your project qualify for our Priority Green Incentive program?:
Expedited
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Is your development site in an environmentally critical area (ECA)?:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Unknown
SIDE SEWER INFORMATION
Related New Construction Project:
6346230
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of Other New Drainage Connections:
1
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
4020
New Impervious Surface:
3018
New Plus Replaced Impervious Surface:
3018
Total Volume Managed by On-Site Stormwater Management (gallons):
1002
Total Area Requiring Soil Amendment:
1002
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of Sewer New/Replaced/Repair Pumps:
1
Number of New Dwelling Units:
8
Reuse Existing Side Sewer System:
No
PARKING
Number of Existing Onsite Parking Spaces:
0
Number of Existing Offsite Parking Spaces:
0
Number of Existing Accessible Parking Spaces:
0
Number of Proposed Onsite Parking Spaces:
0
Number of Proposed Offsite Parking Spaces:
0
Offsite Parking Location:
NA
Number of Proposed Accessible Parking Spaces:
0
Number of Existing Bicycle Parking Spots:
0
Number of Proposed Bicycle Parking Spots:
0