PERMIT APPLICATION COMMON
Choose the Primary Property Use:
Single Family/Duplex
Project Value:
170247
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
02/07/2013
Permit Issued Date:
06/04/2013
Inspections Completed Date:
12/11/2013
Permit Remarks:
Construct and maintain one 20-foot curbcut along S. Judkins St, approximately 42 feet east of west property line. Construct and maintain one 10-foot curbcut along 21st Ave S, approxiamtely 25 feet south of north property line.Temporary Excavation Easement has been granted by owner of 1125 21st Ave S.
CONSTRUCTION VALUATION INFO
Intake Value: New:
170247
Intake Value: Alteration:
0
Total Intake Value:
170247
Issue Value: New:
170247
Issue Value: Alteration:
0
Total Issued Value:
170247
BUILDING CODE INFO
What building code was used for your design?:
2009 SRC
Specific Building Code:
2009 SRC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
3
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Will you change the building use or occupancy?:
Yes
Does your project qualify for our Priority Green Incentive program?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Residential
Compliance Path:
Prescriptive
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
92
HSPF Efficiency (percentage):
0
Heating Fuel Type Proposed: Residential:
Other
SIDE SEWER INFORMATION
Pipe Lining in the Right-of-Way:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
0
Number of Other New Drainage Connections:
1
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
4705
New Impervious Surface:
0
New Plus Replaced Impervious Surface:
3043
Total Volume Managed by On-Site Stormwater Management (gallons):
3043
Total Area Requiring Soil Amendment:
1662
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
No