PERMIT APPLICATION COMMON
Where on your property are you working?:
Onsite + ROW
Choose the Primary Property Use:
Institutional
Project Value:
1019492
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
03/29/2013
Permit Issued Date:
08/28/2013
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
1019492
Intake Value: Alteration:
0
Total Intake Value:
1019492
Issue Value: New:
1019492
Issue Value: Alteration:
0
Total Issued Value:
1019492
BUILDING CODE INFO
What building code was used for your design?:
2009 SBC
Specific Building Code:
2009 SBC
Is this a substantial alteration?:
No
Action Type:
New
Number of Proposed Building Stories:
2
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
1
Tenant Relocation Assistance
Residential Unit Occupancy:
Residential Units on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Prescriptive
SIDE SEWER INFORMATION
Related New Construction Project:
6304888
Temporary Dewatering for Construction:
No
Pipe Lining in the Right-of-Way:
No
Curb Crossing and/or Staging:
Yes
Excavation:
Yes
Curb and Sidewalk Restoration?:
Yes
Roadway Restoration:
Yes
DRAINAGE INFORMATION
Number of Service Drain Lines Capped:
0
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Other New Drainage Connections:
0
Number of Drainage New/Replaced/Repair Pumps:
0
Flow Control Type:
No Control
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
41774
New Impervious Surface:
17927
New Plus Replaced Impervious Surface:
17927
Total Volume Managed by On-Site Stormwater Management (gallons):
20220
Total Area Requiring Soil Amendment:
0
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
0
Sanitary Type of Work:
Addition/Alteration
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
1
Number of Sewer New/Replaced/Repair Pumps:
0
Reuse Existing Side Sewer System:
Yes
PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes