PERMIT APPLICATION COMMON
Choose the Primary Property Use:
Multifamily
Project Value:
4456000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
06/29/2011
Permit Issued Date:
03/14/2012
Inspections Completed Date:
08/08/2013
Certificate of Occupancy Issued Date:
06/20/2013
Permit Remarks:
PASV conducted under project # 3011964 on 01-27-11. MLP
CONSTRUCTION VALUATION INFO
Intake Value: New:
4456000
Intake Value: Alteration:
0
Total Intake Value:
4456000
Issue Value: New:
4760788
Issue Value: Alteration:
0
Total Issued Value:
4760788
BUILDING CODE INFO
What building code was used for your design?:
2009 SBC
Specific Building Code:
2009 SBC
Action Type:
New
Number of Proposed Building Stories:
4
Number of Proposed Below-Grade Building Stories:
0
Number of Mezzanines:
0
Is this a high-rise?:
No
Will you change the building use or occupancy?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Land Disturbing Activity:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
LAND USE STREET ELEMENTS
Number of Curb Cuts for This Permit:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
Unit(s) on Property Not Affected by Scope
WASTE DIVERSION
Waste Diversion Plan Required:
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
No
Elevator Pressurization:
No
Stairway Pressurization:
No
Accessible Elevator Egress:
No
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Component Performance
ENERGY EQUIPMENT
AFUE Efficiency (percentage):
0
HSPF Efficiency (percentage):
0
SANITARY INFORMATION
Reuse Existing Side Sewer System:
No