PERMIT TRACKING COMMON
Review Level:
Dependent Building
Application Completed Date:
07/29/2024
BUILDING CODE INFO
What building code was used for your design?:
2021 SBC
Action Type:
New
Is a certificate of occupancy required?:
Yes
PERMIT APPLICATION COMMON
Where on your property are you working?:
Existing commercial building and parking lot
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Commercial
Project Value:
0
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
Yes
New and Replaced Hard Surface > 750 sq ft?:
Yes
What is the amount of ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
DEMOLITION INFO
Type of Demolition:
Demolition