PERMIT APPLICATION COMMON
Is work in the right-of-way (street or alley) required?:
Yes
Choose the Primary Property Use:
Multifamily
Project Value:
14000000
PERMIT TRACKING COMMON
Review Level:
Full
Application Completed Date:
09/06/2024
Permit Issued Date:
11/13/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
What is the amount of ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
SKYLIC*773DW