PERMIT APPLICATION COMMON
Where on your property are you working?:
Full structural demolition
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
163525
PERMIT TRACKING COMMON
Review Level:
Field
Application Completed Date:
01/30/2024
Permit Issued Date:
01/30/2024
Inspections Completed Date:
03/21/2024
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
No
Excavation:
No
Curb and Sidewalk Restoration?:
No
Roadway Restoration:
No
DRAINAGE INFORMATION
Drainage Type of Work:
None
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
1
Sanitary Type of Work:
Capping Only
Number of New Sewer Connections to the Main:
0
Number of New Connections to the Side Sewer:
0
Number of Sewer New/Replaced/Repair Pumps:
0
Number of New Dwelling Units:
0
Reuse Existing Side Sewer System:
Yes
SIDE SEWER STREET USE INFO
Do you want us to create an SDOT permit application for you, for restoration or staging related to the SDCI Side Sewer permit?:
No
Do you have an existing SDOT permit related to your side sewer work?:
6883873-DM
What is the estimated start date of work in the ROW?:
02/05/2024
What is the estimated duration of work in the ROW (in calendar days)?:
21