PERMIT APPLICATION COMMON
Where on your property are you working?:
Full lot
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
60000000
CONSTRUCTION VALUATION INFO
Intake Value: New:
28446775
Intake Value: Alteration:
0
Total Intake Value:
28446775
Issue Value: New:
28000000
Issue Value: Alteration:
0
Total Issued Value:
28000000
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT Permit Accepted:
Yes
SDOT SIP PM:
Matt Tabalno
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Action Type:
New
Number of Proposed Building Stories:
16
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
Yes
Will you change the building use or occupancy?:
Yes
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is the ground disturbance in an environmentally critical area?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
What is the amount of ground disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Basement
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
10/21/2024
Tenant Relocation Assistance
Are there residential (non-commercial) tenants/renters currently living in the property? :
No
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Sprinklers Meet NFPA 13R:
No
Partial Fire Protection System:
No
Fire Alarm:
Yes
Other Fire Protection System:
No
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
Yes
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
GENCACC867J5