PERMIT APPLICATION COMMON
Where on your property are you working?:
SW corner of 7th Ave
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
17736993.58
PERMIT TRACKING COMMON
Review Level:
Field
Application Completed Date:
05/26/2023
Permit Issued Date:
06/07/2023
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
SIDE SEWER INFORMATION
Temporary Dewatering for Construction:
No
Pipe Lining on Private Property:
No
Pipe Lining in the Right-of-Way:
No
Side Sewer Conflict:
No
Is the system required by the Department of Ecology?:
No
Curb Crossing and/or Staging:
Yes
Excavation:
Yes
Curb and Sidewalk Restoration?:
Yes
Roadway Restoration:
Yes
SIDE SEWER STREET USE INFO
Do you want us to create an SDOT permit application for you, for restoration or staging related to the SDCI Side Sewer permit?:
No
What is the estimated start date of work in the ROW?:
05/31/2023
What is the estimated duration of work in the ROW (in calendar days)?:
2
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
1
Number of Drainage New/Replaced/Repair Pumps:
1
Flow Control Type:
Vault
Flow Control Standard:
Peak
Treatment Standard Type:
No Treatment
Discharge Point:
Combined System
Total Disturbed Area:
13440
New Impervious Surface:
13058
New Plus Replaced Impervious Surface:
13058
Total Volume Managed by On-Site Stormwater Management (gallons):
87542
Total Area Requiring Soil Amendment:
382
SANITARY INFORMATION
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
1
Reuse Existing Side Sewer System:
No