PERMIT APPLICATION COMMON
Where on your property are you working?:
full lot
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Multifamily
Project Value:
5000000
PERMIT TRACKING COMMON
Review Level:
Full C
Application Completed Date:
07/10/2023
Permit Remarks:
Shoring included
FLOATING RESIDENCE INFO
Is this building a Floating Residence?:
No
CONSTRUCTION VALUATION INFO
Intake Value: New:
11127769
Intake Value: Alteration:
0
Total Intake Value:
11127769
Issue Value: New:
11127769
Issue Value: Alteration:
0
Total Issued Value:
11127769
INTERDEPARTMENTAL COORDINATION
SDOT Concept Approval:
Yes
SDOT SIP PM:
KT
BUILDING CODE INFO
What building code was used for your design?:
2018 SBC
Action Type:
New
Number of Proposed Building Stories:
5
Number of Proposed Below-Grade Building Stories:
1
Number of Mezzanines:
0
Is this a high-rise?:
No
Will your application include a new standard plan?:
No
Is a certificate of occupancy required?:
Yes
GROUND DISTURBANCE
Is your development site in an environmentally critical area (ECA)?:
No
New and Replaced Hard Surface > 750 sq ft?:
Yes
Are you doing more than 2,000 square feet of earth disturbance?:
Yes
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Other
Tenant Relocation Assistance
Residential Unit Occupancy:
Some/All Units Occupied by Residential Tenant
Are there residential (non-commercial) tenants/renters currently living in the property? :
Yes
Will the scope of the proposed project displace the tenants/renters?:
Yes
FIRE PROTECTION SYSTEMS
Sprinklers Meet NFPA 13:
Yes
Fire Alarm:
Yes
EMERGENCY SYSTEMS
Are Emergency Systems Required for this Project?:
Yes
Elevator Pressurization:
Yes
Stairway Pressurization:
No
Smoke Removal System:
No
Accessible Elevator Egress:
Yes
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
Yes
ENERGY CODE
Compliance Category:
Commercial
Compliance Path:
Component Performance
SIDE SEWER INFORMATION
Related New Construction Project:
6878334
Temporary Dewatering for Construction:
No
DRAINAGE INFORMATION
Drainage Type of Work:
New
Number of New Drainage Connections to the Main:
3
Flow Control Type:
No Control
Flow Control Standard:
None
Treatment Standard Type:
No Treatment
Discharge Point:
Storm System
Total Disturbed Area:
16469
New Impervious Surface:
305
New Plus Replaced Impervious Surface:
15305
Total Volume Managed by On-Site Stormwater Management (gallons):
106339
Total Area Requiring Soil Amendment:
1164
SANITARY INFORMATION
Number of Service Sewer Lines Capped:
3
Sanitary Type of Work:
New
Number of New Sewer Connections to the Main:
2
Reuse Existing Side Sewer System:
No
CONTRACTOR DISCLOSURE
Who will be performing all the work?:
Licensed Contractor
Contractor License:
KIRTLAL951BC