PERMIT APPLICATION COMMON
Where on your property are you working?:
entire site
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
0
PERMIT TRACKING COMMON
Application Completed Date:
08/26/2020
Permit Issued Date:
08/04/2021
Tenant Relocation Assistance
Residential Unit Occupancy:
No Residential Units on Property
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is the ground disturbance in an environmentally critical area?:
Yes
What is the amount of ground disturbance?:
More than 1 cubic yard
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Foundation Type:
Spread Footing
DEMOLITION INFO
Type of Demolition:
Demolition