PERMIT APPLICATION COMMON
Where on your property are you working?:
In the paved area east of the building.
Is work in the right-of-way (street or alley) required?:
No
Choose the Primary Property Use:
Commercial
Project Value:
40000.00
PERMIT TRACKING COMMON
Review Level:
Full
CONSTRUCTION VALUATION INFO
Total Intake Value:
0
Total Issued Value:
0
BUILDING CODE INFO
What building code was used for your design?:
2015 SBC
Action Type:
Add/Alt
Is a certificate of occupancy required?:
No
GROUND DISTURBANCE
Will your project have ground disturbance?:
Yes
Is your development site in an environmentally critical area (ECA)?:
No
I, the owner or owner’s authorized representative of the property referenced in this submission, give the City of Seattle Department of Planning and Development permission to conduct a Pre-Application Site Visit. I agree that: 1) electronic filing constitutes an authorizing signature; 2) I will inform all tenants of the site visit prior to the inspection being conducted; and 3) if conditions such as uncontrolled dogs or uncooperative tenants hinder the inspector’s ability to conduct the site visit, the site visit will not occur and the site visit fee may be forfeited.:
Yes
Cut Depth in Feet (maximum):
6
Fill Depth in Feet (maximum):
0
Foundation Type:
Other
Does anyone live or work here?:
Yes
Is the disposal site inside the city?:
No
Tenant Relocation Assistance
Residential Unit Occupancy:
Do Not Know-Refer to Property Owner and Tenant Assistance
MECHANICAL CODE
Does your project include an HVAC mechanical system?:
No